| 
                 
                  |  |   
                  | NTPC's Korba super thermal power station: 
                    Located in Chhattisgarh, it is one of Asia's biggest power 
                    plants |   Admittedly, 
                distribution reforms hold the key to commercialising the Indian 
                power sector and converting electricity into just another commodity. 
                Only then will the sector attract investment flows to meet power 
                demand. However, investments cannot wait for the sector to mature, 
                since the demand for power is soaring. Therefore, leading the 
                government's capacity addition programme are central public sector 
                undertakings like National Thermal Power Corporation (NTPC). In 
                the 10th Plan period (2002-2007), the private sector is expected 
                to add a modest 5,000 mw against the central sector, which is 
                expected to contribute around 17,000 mw, a significant part of 
                which is being contributed by NTPC.  Fortunately, it is not a case of fools going 
                where angels fear to tread. Not at least for the last five years, 
                prior to which collections were of the order of 70 per cent, which 
                means for every rupee of power sold, only 70 paise was collected. 
                The receivables were mounting-touching as high as Rs 24,000 crore-and 
                there was little that the Central Power Sector Undertakings (CPSUs) 
                could do. The central government then cut a deal with the states 
                collectively that involved part waiver of the interest component 
                and deferred payment of the outstanding dues. In return, the CPSUs 
                were allowed access to the states' till-that is, the states account 
                with the country's central bank, the Reserve Bank of India-in 
                case of default on power purchased by the utilities. And, lo and 
                behold, the defaults vanished, and overnight collections vaulted 
                to a stunning 99 per cent.   With this gilt-edged safeguard, CPSUs are 
                better placed than the private sector in the business of capacity 
                addition. For one, it significantly insulates the CPSUs from recovery 
                losses, which are about 35 per cent. The private sector, on the 
                other hand, has to factor in the losses while financing its projects. 
                However, the CPSU's ability to finance projects is also limited, 
                as lenders look to the cash flow volume to secure their debts 
                (apparently, the fact that they can tap the state's account with 
                RBI is not a big assurance). Hence, while NTPC is capable of adding 
                around 22,000 mw in the 11th Plan period (2007-2012), based on 
                its ability to service its debt liabilities, it is currently targeting 
                only around 17,000 mw. 
                 
                  | THE LURE OF SPOT MARKETS Why short-term contracts are more lucrative.
 |   
                  | Traditionally, 
                    generators in the country that sell power to the utilities 
                    have earned a fixed return set by the regulator. This, since 
                    power procurement has hardly occurred on a competitive basis 
                    owing to legacy issues that have destroyed the commercial 
                    viability of the sector. Therefore, only government-driven 
                    investments are the dominant ones. For example, NTPC's plants 
                    account for 25 per cent of the country's supply and all of 
                    its plants earn a flat 14 per cent return on equity. But in 
                    the newer plants, NTPC is going 'merchant'-that is, not tying 
                    up capacity to long-term contracts that would immediately 
                    attract the regulator's eye. So far, it has quietly shored 
                    up 2,000 mw of capacity that will mature in a few years. This, 
                    in turn, will spur the short-term power market development, 
                    where returns are not capped.  Unlike NTPC, some of the states like Orissa that prudently 
                      added capacity are able to earn huge bounties from buyers 
                      like Uttar Pradesh, where demand vastly outstrips supply. 
                      Uttar Pradesh sometimes pays as much as Rs 5 per unit, as 
                      against Orissa's generation cost of Rs 1.50 per unit. Interestingly, 
                      the transaction price is dependent on not only the demand-supply 
                      position, but also regulatory intervention. The prevailing 
                      deficit situation often results in several states over-drawing 
                      power beyond their schedule. This results in the frequency 
                      dipping below the critical level. To avert this situation, 
                      the regulator imposes stiff penalty on those who over-draw 
                      power. This, incidentally, sets the alternate cost of purchase 
                      of power for the deficit utility. Evidently, NTPC is setting 
                      a trend where a part of its new capacity is being created 
                      on a merchant basis. And with the distribution sector maturing, 
                      more generators may follow suit. And power sector stocks 
                      will no longer have to suffer their traditional description-orphan 
                      stocks. |  Courting Private Producers   With power demand rising at around 8 per 
                cent annually over the last two years, led by industrial demand 
                that has grown at 11 per cent a year, the power ministry is targeting 
                around 62,000 mw capacity addition in the 11th Plan period. (Just 
                for the record, India has an energy shortage of 7.8 per cent and 
                a peak shortage of 11.23 per cent.) Of this, CPSUs are expected 
                to contribute 31,000 mw, the state sector 20,000 mw and the private 
                sector, the remaining 11,000 mw.   And this forms the basis of the central government's 
                argument for promoting private capacity addition. Over the last 
                two years, the vehicle for this promotion is a multi-disciplinary 
                group, called the Inter Institutional Group (IIG), involving governmental 
                financial institutions. Here, only those private projects with 
                competitive tariffs were taken up and their last mile problems 
                solved. Subtle arm-twisting became commonplace-states were often 
                told that if they delayed signing up competitive projects, they 
                would be denied additional power supply from the central generating 
                stations.   This process lost its relevance when the 
                problems of the 'pre-cooked' competitive projects were addressed 
                one way or another-several projects were turned away when they 
                failed to line up gas supplies. There was, however, one project 
                that did not take off owing to the perception of the promoters' 
                credentials. The financial institutions refused to finance a 1,000-mw 
                project promoted by Jaiprakash Industries when they found that 
                the equity component in the project fell below the 30 per cent 
                mark during the course of the project. The FIIs, having burnt 
                their fingers with the Enron-promoted Dabhol project, were not 
                willing to take chances. At final count, the IIG process saw through 
                around 8,000 mw of private capacity.   In what appears to be the next level of intervention, 
                the central government is undertaking a key, yet 'soft', aspect 
                of project development-obtaining the various clearances like land, 
                environment, domestic captive mine, and tying power sale with 
                several states. However, the role is limited to that of facilitation 
                and not that of providing any financial comforts to mitigate the 
                payment risks posed by the purchasing utilities, and that continues 
                to be the critical issue bogging down the sector. The other salient 
                feature of this intervention is the scaling up of projects-4,000 
                mw apiece-in a bid to reduce power costs. The power ministry is 
                upbeat on the prospects, based on the initial response, which 
                has seen more than 30 companies buy the Request for Qualification 
                (RFG) document. Says Power Secretary R.V. Shahi: "The Sasan 
                and Mundhra projects are very much on schedule. The projects will 
                be awarded by the end of the year." While the Madhya Pradesh-based 
                Sasan project will operate on domestic coal, the Gujarat-based 
                Mundhra project is planned to operate on imported coal.   The Tariff Challenge  
                 
                  |  |   
                  | NTPC Chairman T. Shankaralingam: The 
                    corporation's plants account for around 25 per cent of the 
                    country's supply |  To be sure, some big announcements have come 
                recently from the private sector. Tata Power, for instance, has 
                bid for four mega projects, and has already received the RFG for 
                the Sasan and Mundhra projects. Anil Ambani's Reliance Energy, 
                on the other hand, has plans that span nuclear to hydel and envisage 
                Rs 60,000 crore in investment. However, the litmus test for the 
                mega projects will be the response to the next stage of the bid 
                process, where tariffs will be solicited. It is here that the 
                risk perception of the sector will be truly discovered. "We 
                have decided against bidding for the ultra mega projects since 
                the fundamental issue of payment security from the purchasing 
                utilities has not been addressed. And, it is not as if our appetite 
                in the power generation business has been whetted," says 
                Praveer Sinha, Chief Operating Officer, Nagarjuna Power Corporation, 
                which has already inked a deal to sell power to the Karnataka 
                state distribution utility power from its proposed 1,015 mw imported 
                coal-based plant in Mangalore.   The response from one of the bidders is no 
                less cautious. Says Srinivasa Rao, Country Head, AES (India) Ltd, 
                a subsidiary of the global power major AES Corporation: "We 
                have serious concerns about the payment security mechanism as 
                reforms have not progressed adequately. Furthermore, the government 
                could have considered several units of 1,000 mw each, as it would 
                be easier to secure finances for them rather than a single 4,000-mw 
                project in view of the payment risks involved."   Ironically, it is one of the Centre's reform 
                measures that will put pressure on the utilities' payment abilities-to 
                recall, the utilities' deal with the PSUs five years ago, wherein 
                they secured future power bill payments in lieu of partial waivers. 
                While the move became a reform driver since payment became a zero-sum 
                game (either the utilities paid up in full to the central sector 
                power utilities like NTPC or its owner, the state, would cough 
                up the payments), matching distribution reforms have not taken 
                place. Hence, the payment security mechanism for PSUs (which supply 
                over 25 per cent of the country's power) will put pressure on 
                the utilities' payment ability for future capacity addition. Furthermore, 
                the states' finances will now be further strained, since the time 
                is ripe for redemption of bonds issued to NTPC five years ago 
                in lieu of their outstanding dues. Every six months, the states 
                will have to pay around Rs 1,000 crore to NTPC.  
                 
                  |  |   
                  | AES' Rao: Has serious concerns about 
                    the payment security mechanism for the ultra mega projects |  In fact, the regulator for multi-state power 
                transfers, Central Electricity Regulatory Commission (CERC), has 
                already 'advised' the government that it must identify escrow 
                capacity, or revenue streams from the utilities' distribution 
                business, that remain unencumbered. The idea: in case of payment 
                defaults, the sponsors of the ultra mega power projects will have 
                direct access to this cash flow. "We are here to facilitate 
                capacity creation at every level. However, we have voiced our 
                concern to the government on the need to ensure a robust payment 
                security mechanism so that the projects are viable," says 
                A.K. Basu, Chairman, CERC. "We have also told the government 
                that such large capacities should be entirely contracted by the 
                utilities on a long-term basis," he added. This typically 
                mirrors the lenders' views, who finance as much 70 per cent of 
                the project cost. Says Jitendra Balakrishnan, Deputy MD, IDBI: 
                "The ultra mega projects are at a preliminary stage and there 
                are issues relating to payment security and imported fuel that 
                we are attempting to address."   It is not as if the private sector is sitting 
                pretty on the ringside. Realising the criticality of fuel in the 
                final power cost, private sponsors are flocking to the coal-bearing 
                states, as domestic coal continues to be the best bet, never mind 
                hurdles like law and order issues. "We have proposals for 
                as much as 18,000 mw of capacity addition in our state. And a 
                good part of this capacity will be exported to other states," 
                says Chhattisgarh State Electricity Board chairman Rajib Ranjan. 
                  With state power utilities allocating as 
                much as 80 per cent of their costs on purchase of power, the key 
                issue facing the sector is the ability to add reasonably priced 
                power capacity. For the market, higher risk will demand higher 
                returns. So don't expect the private sector to be swept off its 
                feet by the suitor at the Centre. |