India's economy has expanded
more than 8.5 per cent annually over the past four years, but
a widening gap between the demand and supply of electricity threatens
to derail the country's growth. The power sector in the country
is by and large run by state governments, which have been slow
in adding new capacities due to a lack of funds. Although the
sector was opened to private capital more than a decade ago, few
companies have invested in building new plants because of regulatory
bottlenecks.
It is estimated during peak hours, demand outstrips supply by
as much as 25 per cent in some parts of the country, causing frequent
outages and coercing shutdowns at factories and businesses. To
deal with the issue, there is a need to build hundreds of new
power plants over the next five years to end the massive electricity
shortages.
The Eleventh Plan can be the perfect juncture to give power
sector a right swing. The National Development Council has mandated
that the Eleventh Five Year Plan should aim at the twin objective
of achieving faster and more inclusive growth. Under the plan,
the Government has set a target of around 78,000 MW of additional
capacity. Both these objectives require a massive improvement
in the situation facing the power sector.
However, the report card of the previous plan makes it look
oblique. In the Tenth Plan period, against a target of adding
41,000 MW, the country's actual achievement was only a little
over 21,000 MW. Nonetheless, the task of adding 78,000 MW, even
including the spillover capacity of 11,000 MW is a tall order.
The background papers indicate that nearly 49,000 MW of capacity
is currently in the process of being implemented. It is estimated
that with a determined effort, orders could be placed for another
29,000 MW by the end of December. Both the Centre and the States
must give the highest priority to ensuring that these orders are
indeed placed.
It is also necessary to ensure that these projects, once underway,
are actually completed on time. Power projects are very often
held up for want of coal linkages and environmental clearances
which are beyond the purview of state governments. Some mechanism
of inter-governmental consultation is essential to accelerate
resolution of these bugbears.
Apart from adding new plants, the state governments have to
take measures to prevent high losses during transmission and distribution,
which also include theft of electricity. The current growth target
certainly requires a much faster increase in supply of electricity
with much less dependence on high cost captive power.
The task of expanding generation capacity by 78,000 MW is not
only managerially tough; it also presents a financing challenge.
The cost of creating generation capacity on this scale is about
Rs 3.5 trillion. Applying the general rule that for every rupee
spent in generation it is necessary to spend the same amount on
transmission and generation, the total investment required in
the power sector in the Eleventh Plan to operationalise the targeted
additional capacity would have to be over Rs 7 trillion. The country
also needs to provide for the massive backlog in investment in
distribution because of neglect of this sector in the past. Without
such investment it will not be possible to achieve improvements
in quality of power and loss reduction for the existing system.
|