On
January 30, the top brass of the beleaguered Ratnagiri Gas &
Power Private Ltd (RGPPL)-the new avatar of Dabhol Power Company
(DPC)-and Power Secretary R.V. Shahi were closeted for hours with
Cabinet Secretary B.K. Chaturvedi. Its promoters-NTPC (National
Thermal Power Corporation) and GAIL (Gail India Ltd), which hold
28 per cent equity each in RGPPL-wanted, among other things, Chaturvedi
to intervene and get Operations & Maintenance (O&M) contractor
Bharat Heavy Electrical Ltd (BHEL) to reduce its revised offer
for the revival of the mothballed plant.
BHEL's bill for restarting the 740 mw Block
II of the Dabhol project, that had been lying idle for five years:
Rs 214 crore. "If this figure is extrapolated across the
entire project, the cost of restarting the three blocks (I, II
and III) will swell to Rs 870 crore," Shahi explained to
the Cabinet Secretary. "Only three years back, the Belgium-based
Tractabel, a consultant appointed by Dabhol's lenders, had estimated
that it would cost Rs 214 crore to revive the entire project (Blocks
I, II and III)," Shahi told Chaturvedi. The obvious inferences:
BHEL's bill is unreasonably high (see Is BHEL Overcharging?),
and that "such a high cost of revival will result in very
high tariffs". Counters a top BHEL official: "You just
cannot extrapolate the figures for reviving Block I to the other
two blocks. The rates we have quoted may come down marginally
if we get the contract for all the three blocks. But any further
delays may lead to higher costs." RGPPL also wants BHEL to
supply materials, spares and consumables at prices comparable
to what GE and Alstom are charging for NTPC's 645 mw Kawas plant.
Here, too, BHEL refuses to play ball. "They (NTPC's Kawas
and Dabhol) are not comparable as the former was a greenfield
project while the latter is an existing one where lots of overhauling
and restoration activities have to be done," says the BHEL
official.
Using naphtha will result
in a power cost of Rs 7.5 per unit, which is what Enron planned
to charge five years ago. And if the Maharashtra government
offers power at a subsidised rate of Rs 2.30 per unit, the
MSEB will have to bear huge losses |
But this is only the easier part of the problem.
BHEL, after all, is a public sector company, and can be pressurised
to fall in line. The supply of liquefied natural gas (LNG), the
preferred fuel for the plant, presents a more intractable problem.
Why? Because there is no LNG in sight, at least as of now. And
even if LNG can be procured from the international market, the
plant lacks the facilities to process it. Its 2.1 million tonnes
per annum (mtpa) LNG terminal is only 75 per cent complete. GE
and Bechtel, the plant's original contractors, have agreed to
help RGPPL complete the project, but no agreement has been reached
on the issue yet. "We took over the assets (from DPC) towards
the end of 2005. We are now studying the extent of damage it has
suffered (due to closure) and will commission the balance work
once this is over," says O.P. Gupta, General Manager, who
has been deputed from NTPC to RGPP;. Yogesh Tripathi, Senior Manager,
Punj Lloyd, refuses to set a time frame for completion of the
terminal. Punj Lloyd, Whessoe and Aker Kvaerner are the contractors
for the revival of the LNG facility. Paul Sullivan, Director (Business
Development), Whessoe, says: "The report will be complete
around March-end. Based on this report, RGPPL will negotiate a
contract with the Whessoe-led team to complete the project."
RGPPL had set an internal target of commencing
commercial production of power from July 1, 2006, subject to the
availability of LNG. Newly appointed Union Power Minister Sushil
Kumar Shinde has, in fact, committed to starting the plant in
June. Now, the RGPPL brass is under pressure to start the plant
in June this year using the more costly naphtha as fuel. The infrastructure
for handling naphtha is not yet ready. GAIL, which is setting
it up, has indicated that it may be in a position to deliver within
the stipulated time "on a best effort basis". Naphtha,
however, will increase the cost of power to over Rs 7.5 per unit,
which is the same as Enron's price some five years back. The implication
is obvious: if power has to be supplied to end users at Rs 2.30
per unit, the Maharashtra State Electricity Board (MSEB) will
have to bear huge losses. Sources connected with the project,
however, say the Maharashtra government may not mind this, as
it currently pays over Rs 7 per unit for power drawn from NTPC's
Kawas plant during peak hours.
A TWISTED SAGA |
In 1993, the
Houston-based Enron corporation signed a memorandum of understanding
(MoU) with the Congress government in Maharashtra to build
a $3 billion (Rs 9,600 crore at the exchange rate prevailing
then) power plan at Dabhol. The Shiv Sena-BJP government,
which came to power in 1995, scrapped the project, and forced
Enron to renegotiate the deal on less favourable terms to
itself. But despite this, the Maharashtra State Electricity
Board (MSEB) was forced to buy power from the Dabhol Power
Company (DPC) at over Rs 7 per unit compared to Rs 2-3 per
unit which it was paying for power from coal-based plants.
In November 2000, it defaulted on its dues. DPC invoked the
central government's counter-guarantee and sparked off bitter
litigation and arbitration. In December 2001, however, Enron
was indicted for fraud and slipped into bankruptcy in the
US. GE and Bechtel bought out Enron's 65 per cent equity stake
(for some $20 million or Rs 90 crore) in DPC, taking their
combined stake to 85 per cent. Then, in July 2005, following
long-drawn, bare-knuckle negotiations amongst the various
stakeholders, GE, Bechtel and the foreign lenders were paid
off and the project taken over by Ratnagiri Gas & Power
Private Ltd (RGPPL), a joint venture between NTPC and GAIL
India Ltd. |
But running the Dabhol plant on naphtha will
not be viable over the long term; it has to switch to LNG at the
earliest. Five months after RGPPL took over Dabhol's assets, GAIL,
which has the contract for sourcing the fuel, is still to tie
up any long-term LNG contracts. The spot prices of LNG, which
soared to a high of $13-15 (Rs 585-675) per MBTU (million British
thermal unit) in August-September last year, are currently ruling
at the still high levels of $7.5-8.5 (Rs 337.5-382.5) per MBTU.
At these prices, power from Dabhol will cost Rs 6 per unit. Even
here, there's a fly in the ointment: not much spare LNG capacity
is available till 2010 (see Countries Where...). "As things
stand today, we have to aggregate LNG supplies from more than
one supplier," says an RGPPL exec.
Oman LNG, the original gas supplier for the
plant, is playing hide and seek with RGPPL. Sources say Oman LNG
refused to sign a confidentiality agreement with RGPPL. "It
has also not responded to a spot LNG purchase agreement we sent
it in December last year," add sources. Oman LNG has 0.6
mmtpa (million metric tonnes per annum) spare LNG capacity which
is critical to RGPPL's plans of switching over to the fuel by
September this year. "We will meet Oman LNG in the first
week of March to sort out the matter," says an RGPPL executive.
Negotiations are also on in this regard with companies in Qatar,
Australia, Abu Dhabi, Brunei and several other countries, but
"prices quoted by most of the suppliers are as high as $7
(Rs 315) per MBTU."
LNG supplies will definitely be tied up,
but they will come at a price that may not look very attractive
to RGPPL. The company may also not be in a position to cross-subisidise
its power sales as the additional merchant sales capacity (commercial
sale of LNG at market rates) of 2.9 mtpa will not become operational
before September 2007, which is still about 20 months away. This
last bit is crucial. The commercial viability of RGPPL depends
critically on operating its 5 mtpa LNG plant at full capacity
and generating additional resources from the commercial sale of
2.9 mtpa.
So, five years after the now bankrupt Enron
Corporation's Dabhol power project was mothballed and five months
after it was taken over by RGPPL, there's still no certainty over
whether this mega power project can actually produce electricity
at commercially viable rates.
|