| On 
                January 30, the top brass of the beleaguered Ratnagiri Gas & 
                Power Private Ltd (RGPPL)-the new avatar of Dabhol Power Company 
                (DPC)-and Power Secretary R.V. Shahi were closeted for hours with 
                Cabinet Secretary B.K. Chaturvedi. Its promoters-NTPC (National 
                Thermal Power Corporation) and GAIL (Gail India Ltd), which hold 
                28 per cent equity each in RGPPL-wanted, among other things, Chaturvedi 
                to intervene and get Operations & Maintenance (O&M) contractor 
                Bharat Heavy Electrical Ltd (BHEL) to reduce its revised offer 
                for the revival of the mothballed plant.   BHEL's bill for restarting the 740 mw Block 
                II of the Dabhol project, that had been lying idle for five years: 
                Rs 214 crore. "If this figure is extrapolated across the 
                entire project, the cost of restarting the three blocks (I, II 
                and III) will swell to Rs 870 crore," Shahi explained to 
                the Cabinet Secretary. "Only three years back, the Belgium-based 
                Tractabel, a consultant appointed by Dabhol's lenders, had estimated 
                that it would cost Rs 214 crore to revive the entire project (Blocks 
                I, II and III)," Shahi told Chaturvedi. The obvious inferences: 
                BHEL's bill is unreasonably high (see Is BHEL Overcharging?), 
                and that "such a high cost of revival will result in very 
                high tariffs". Counters a top BHEL official: "You just 
                cannot extrapolate the figures for reviving Block I to the other 
                two blocks. The rates we have quoted may come down marginally 
                if we get the contract for all the three blocks. But any further 
                delays may lead to higher costs." RGPPL also wants BHEL to 
                supply materials, spares and consumables at prices comparable 
                to what GE and Alstom are charging for NTPC's 645 mw Kawas plant. 
                Here, too, BHEL refuses to play ball. "They (NTPC's Kawas 
                and Dabhol) are not comparable as the former was a greenfield 
                project while the latter is an existing one where lots of overhauling 
                and restoration activities have to be done," says the BHEL 
                official.  
                 
                  | Using naphtha will result 
                    in a power cost of Rs 7.5 per unit, which is what Enron planned 
                    to charge five years ago. And if the Maharashtra government 
                    offers power at a subsidised rate of Rs 2.30 per unit, the 
                    MSEB will have to bear huge losses |  But this is only the easier part of the problem. 
                BHEL, after all, is a public sector company, and can be pressurised 
                to fall in line. The supply of liquefied natural gas (LNG), the 
                preferred fuel for the plant, presents a more intractable problem. 
                Why? Because there is no LNG in sight, at least as of now. And 
                even if LNG can be procured from the international market, the 
                plant lacks the facilities to process it. Its 2.1 million tonnes 
                per annum (mtpa) LNG terminal is only 75 per cent complete. GE 
                and Bechtel, the plant's original contractors, have agreed to 
                help RGPPL complete the project, but no agreement has been reached 
                on the issue yet. "We took over the assets (from DPC) towards 
                the end of 2005. We are now studying the extent of damage it has 
                suffered (due to closure) and will commission the balance work 
                once this is over," says O.P. Gupta, General Manager, who 
                has been deputed from NTPC to RGPP;. Yogesh Tripathi, Senior Manager, 
                Punj Lloyd, refuses to set a time frame for completion of the 
                terminal. Punj Lloyd, Whessoe and Aker Kvaerner are the contractors 
                for the revival of the LNG facility. Paul Sullivan, Director (Business 
                Development), Whessoe, says: "The report will be complete 
                around March-end. Based on this report, RGPPL will negotiate a 
                contract with the Whessoe-led team to complete the project." 
                  RGPPL had set an internal target of commencing 
                commercial production of power from July 1, 2006, subject to the 
                availability of LNG. Newly appointed Union Power Minister Sushil 
                Kumar Shinde has, in fact, committed to starting the plant in 
                June. Now, the RGPPL brass is under pressure to start the plant 
                in June this year using the more costly naphtha as fuel. The infrastructure 
                for handling naphtha is not yet ready. GAIL, which is setting 
                it up, has indicated that it may be in a position to deliver within 
                the stipulated time "on a best effort basis". Naphtha, 
                however, will increase the cost of power to over Rs 7.5 per unit, 
                which is the same as Enron's price some five years back. The implication 
                is obvious: if power has to be supplied to end users at Rs 2.30 
                per unit, the Maharashtra State Electricity Board (MSEB) will 
                have to bear huge losses. Sources connected with the project, 
                however, say the Maharashtra government may not mind this, as 
                it currently pays over Rs 7 per unit for power drawn from NTPC's 
                Kawas plant during peak hours.  
                 
                  | A TWISTED SAGA |   
                  | In 1993, the 
                    Houston-based Enron corporation signed a memorandum of understanding 
                    (MoU) with the Congress government in Maharashtra to build 
                    a $3 billion (Rs 9,600 crore at the exchange rate prevailing 
                    then) power plan at Dabhol. The Shiv Sena-BJP government, 
                    which came to power in 1995, scrapped the project, and forced 
                    Enron to renegotiate the deal on less favourable terms to 
                    itself. But despite this, the Maharashtra State Electricity 
                    Board (MSEB) was forced to buy power from the Dabhol Power 
                    Company (DPC) at over Rs 7 per unit compared to Rs 2-3 per 
                    unit which it was paying for power from coal-based plants. 
                    In November 2000, it defaulted on its dues. DPC invoked the 
                    central government's counter-guarantee and sparked off bitter 
                    litigation and arbitration. In December 2001, however, Enron 
                    was indicted for fraud and slipped into bankruptcy in the 
                    US. GE and Bechtel bought out Enron's 65 per cent equity stake 
                    (for some $20 million or Rs 90 crore) in DPC, taking their 
                    combined stake to 85 per cent. Then, in July 2005, following 
                    long-drawn, bare-knuckle negotiations amongst the various 
                    stakeholders, GE, Bechtel and the foreign lenders were paid 
                    off and the project taken over by Ratnagiri Gas & Power 
                    Private Ltd (RGPPL), a joint venture between NTPC and GAIL 
                    India Ltd. |  But running the Dabhol plant on naphtha will 
                not be viable over the long term; it has to switch to LNG at the 
                earliest. Five months after RGPPL took over Dabhol's assets, GAIL, 
                which has the contract for sourcing the fuel, is still to tie 
                up any long-term LNG contracts. The spot prices of LNG, which 
                soared to a high of $13-15 (Rs 585-675) per MBTU (million British 
                thermal unit) in August-September last year, are currently ruling 
                at the still high levels of $7.5-8.5 (Rs 337.5-382.5) per MBTU. 
                At these prices, power from Dabhol will cost Rs 6 per unit. Even 
                here, there's a fly in the ointment: not much spare LNG capacity 
                is available till 2010 (see Countries Where...). "As things 
                stand today, we have to aggregate LNG supplies from more than 
                one supplier," says an RGPPL exec.   Oman LNG, the original gas supplier for the 
                plant, is playing hide and seek with RGPPL. Sources say Oman LNG 
                refused to sign a confidentiality agreement with RGPPL. "It 
                has also not responded to a spot LNG purchase agreement we sent 
                it in December last year," add sources. Oman LNG has 0.6 
                mmtpa (million metric tonnes per annum) spare LNG capacity which 
                is critical to RGPPL's plans of switching over to the fuel by 
                September this year. "We will meet Oman LNG in the first 
                week of March to sort out the matter," says an RGPPL executive. 
                Negotiations are also on in this regard with companies in Qatar, 
                Australia, Abu Dhabi, Brunei and several other countries, but 
                "prices quoted by most of the suppliers are as high as $7 
                (Rs 315) per MBTU."  LNG supplies will definitely be tied up, 
                but they will come at a price that may not look very attractive 
                to RGPPL. The company may also not be in a position to cross-subisidise 
                its power sales as the additional merchant sales capacity (commercial 
                sale of LNG at market rates) of 2.9 mtpa will not become operational 
                before September 2007, which is still about 20 months away. This 
                last bit is crucial. The commercial viability of RGPPL depends 
                critically on operating its 5 mtpa LNG plant at full capacity 
                and generating additional resources from the commercial sale of 
                2.9 mtpa.  So, five years after the now bankrupt Enron 
                Corporation's Dabhol power project was mothballed and five months 
                after it was taken over by RGPPL, there's still no certainty over 
                whether this mega power project can actually produce electricity 
                at commercially viable rates.  |